The boring of the Bolaños tunnel has been completed. The works have created two parallel single-track tunnels, each 6.7 km long. It reported that with an average excavation performance of 19.40 linear m/d in the first tunnel, the work took 11.5 months to complete, the boring of the second tunnel saw an average excavation performance of 24.32 linear m/d, and so the work took 9.5 months to finish.

The works use a particular innovative solution for the construction of the tunnels, that involved the application of a stabilization system for land of high geological instability.